Challenge

The client was required to obtain a permit for the transfer of existing Pulverised Fuel Ash (PFA) landfill from RWE to Ingrebourne Valley (IV) and a variation of landfill permit to enable disposal of tunnelling spoil from Thames Tideway Tunnelling (TTT) project and mining of PFA.

Solution

SLR’s role on the project included the preparation of applications to transfer and vary the permit and also the production of supporting technical assessments including Hydrogeological Risk Assessment Review, Stability Risk Assessment, Dust Management Plan, Gas Risk Assessment, Conceptual Design.

Impact

SLR negotiated a reduction of the site’s aftercare period from 60 years to 3 years, saving the client £100,000s in costs for aftercare monitoring and insurance bonds for financial provision.

The environmental permit was successfully secured, with a further outcome of the project being the secured recovery of waste status for low permeability cap, cap protection layer and restoration soils saving landfill tax applying to 1.22 million m3 of waste to be imported to the site.


Related projects

See all projects
  • Project

    Victoria, Australia

    Cleanaway

    Infrastructure

    Tottenham resource recovery and container deposit scheme project


    Read more
  • Project

    New South Wales, Australia

    Telstra InfraCo

    Technology, Media & Telecoms

    Flora and fauna assessment for Woolgoola telecommunications


    Read more
  • Project

    Brooklyn, Victoria, Australia

    DB Architects

    Built Environment

    Cougar Recycling - site management & stormwater drainage design


    Read more